Middle Tennessee Lane Closure Report February 21-23, 2022
DAVIDSON COUNTY, I-24
The random on-call signing on various Interstate and State Routes mm46.5 – 47
- Nightly, 8 p.m. – 5 a.m., There will be nighttime partial ramp lane closures for extruded panel sigh installation.
The resurfacing on I-24 including bridge repair from the I-40 split to the I-440 split, mm 51 – 53
- Daily, 9 a.m. – 3 p.m., There will be multiple shoulder closures on I-24 between the I-40 split and the I-440 split for ITS work.
The grading, drainage, construction of a retaining wall, signals and paving on I-24 at the EB exit ramp to SR 254 (Bell Rd., Exit 59)
- Nightly, 8 p.m. – 5 a.m. (excluding weekends), There will be lane closures on I-24 EB for traffic shift and construction activities.
The resurfacing on I-24 including bridge repair from the I-40 split to the I-440 split
- Nightly, 8 p.m. – 5 a.m. There will be multiple, alternating lane closures and multiple, alternating ramp closures on I-24 between the I-40 split and the I-440 split for traffic loops and striping.
DAVIDSON COUNTY, I-40
The resurfacing on I-40 from Old Hickory Blvd. to Arlington Ave (mm 216-217)
- Daily (excluding weekends), 9 a.m. – 3 p.m. There will be multiple shoulder closures on I-24 between the I-40 split and the I-440 split for ITS work.
The resurfacing on I-40 from Old Hickory Blvd. to Arlington Ave.
- Nightly, (excluding weekends), 8 p.m. – 5 a.m., There will be multiple shoulder closures on I-24 between the I-40 split and the I-440 split for ITS work.
DAVIDSON / RUTHERFORD COUNTY I-24
The construction of an Intelligent Transportation System and upgrades from Nashville to Murfreesboro (Part 2) , mm 53- mm80
- Nightly, 8p.m. – 5 a.m., There will be left lane closures EB and WB for overhead sign foundation work in the median from MM 53 to MM 65. Two lanes will remain open at all times.
ROBERTSON COUNTY, I-24
The random on-call signing on various Interstate and State Routs mm 19 – 20
- Nightly, 8 p.m. – 5 a.m., There will be nighttime lane closures for extruded panel sigh installation.
ROBERTSON COUNTY, I-65
Grading, drainage, construction of bridges and retaining walls, ITS and paving mm108 – 119
- Nightly, 8 p.m. – 5 a.m. Milling and Paving Operations. North and South directions. Troopers to be utilized. Ramps to be closed nightly when activity is performed in those areas. 1 ramp will be closed at a time. Ramp to be operational again the following morning.
RUTHERFORD COUNTY I-840
The resurfacing on I-840 including concrete ramp repair
- 2/19, 5 a.m. – 12 p.m., The exit ramp from I-840 to SR 102 (Exit 47) will be closed for concrete ramp grooving
WILLIAMSON COUNTY I-840,
The repair of the bridges on I-840 over South Garrison Branch mm 15.2 – 17.4
- 24/7, I-840 WB lane will be closed to do bridge repair work. WB traffic will be shifted to the EB side lane 1, all EB traffic will be running on lane 2/shoulder. Traffic will remain in one lane, for both directions for the entirety of the project.
WILSON COUNTY, I-40
Bridge widening on SR 171 over I-40 – from mm 225 to mm 226
- Nightly, 8 p.m. – 5 a.m., I-40 EB and WB will have intermittent lane closures for bridge widening activities.
The random on-call signing on various Interstate and State Routes
- Nightly, 8 p.m. – 5 a.m., There will be nighttime lane closures for extruded panel sign installation.
CHEATHAM COUNTY SR 455
Grade, drain, pave of SR 455 + Levee construction (by others)
- 24/7, Continuous Full Road closure for the construction of levee (by others), box culvert, stream relocation and roadway construction from SR 49 to AO Smith entrance. Riverbluff Park entrance will remain open to the public. Access to AO Smith from SR 12 will remain open.
DAVIDSON COUNTY, SR 1
The resurfacing on SR 1 from near south of Woodmont Blvd. (LM 13) to 15th Ave. (LM 17)
- Nightly, 8 p.m. – 5 a.m., (including weekends), There will be multiple, alternating lane closures for guardrail, concrete and utility adjustment operations.
Full and partial depth repair of Portland Cement Concrete pavement and sidewalk on US 41 (US 70S, SR 1 Murfreesboro Road) from near Fesslers Lane (LM 20) to near Foster Ave (mm 20 – mm 20.32)
- Continuous, There will be alternating lane closures on Murfreesboro Rd from Fesslers Lane to Foster Ave to remove and repour damaged concrete.
- Nightly, excluding weekends, 8 p.m. – 5 a.m., There will be alternating lane closures on Murfreesboro Rd from Fesslers Lane to Foster Ave to remove damaged concrete.
DAVIDSON COUNTY, SR 112
SR 112 (US 41A/Clarksville Pike) from SR 12 (Ashland City Highway) to SR 155 (Briley Parkway) – Piedmont Move Prior
- Daily, 9 a.m. – 3 p.m. There will be a temporary alternating lane closure on SR 112 Clarksville Pike in both directions for grade work, storm drainage, sanitary sewer and overhead power. Flaggers will be utilized. There will also be a full closure of Fairview Drive for road grading and underground communications; detour will be in place.
MACON COUNTY, SR 52
Traffic Signal Installation at Ellington Drive
- Daily, 9 a.m. – 3:30 p.m., There will be intermittent lane closures on SR 52 at Ellington Drive for Traffic Signal installation.
MONTGOMERY COUNTY SR 12
Bicycles and Pedestrian Facilities mm16.8 – 19.3
- Daily, 9 a.m. – 3 p.m., Sidewalk construction. Contractor to utilize 1 lane of traffic for safety and construction.
MONTGOMERY COUNTY SR 13
Consisting of: the grading, drainage, construction of welded steel plate girder bridge, retaining wall and paving on S.R. 149 and S.R. 13 from River Road to Zinc Plant Road. MM 17-19
- Daily, 7 a.m. – 5 p.m., bridge work, and/or paving operations. Mayhew Road will remain closed. Traffic on SR 13 will remain in the phase four alignment as switched on 11/7/20. Width reduced to 22′ for entire project.
MONTGOMERY COUNTY SR 76 AND SR 112
Intersection Improvements. Grading, Drainage and Construction of Retaining walls.
- Daily, 9 a.m. – 3 p.m., Grading Operations, Lane closures will be intermittent
RUTHERFORD COUNTY SR 1
LPLM: Town of Smyrna Street Scapes on SR 1
- Daily, 9 a.m. – 3 p.m., There will be alternating lane closures for construction activities.
RUTHERFORD COUNTY, 266
The grading, drainage, construction of two concrete bulb tee beam bridges, signals, and paving on SR 266 (Jefferson Pike) from SR 102 (LM 5.0) to east of I-840 (LM 9).
- 2/22, 9 a.m. – 2:30 p.m., There will be flagging operations and short duration closures (5-10 min) for beam setting operations at bridge over Stones River.
SUMNER COUNTY SR 25
Gateway Drive Extension
- Daily, 9 a.m. – 3:30 p.m., There will be intermittent lane closures on SR 25 near Barry Lane for road widening activities.
SUMNER COUNTY, SR 174
Local Programs: Goodlettsville traffic flow improvements and traffic signal upgrades
- Daily, 9 a.m. – 3 p.m. There will be a lane closure on eastbound SR-174 (Long Hollow Pk) before Caldwell Dr for construction of a concrete island and curb ramps.
WILLIAMSON COUNTY SR 6
Grading, drainage and paving work on SR 6 (Franklin Road) from south of Moore’s Lane (LM 15.93) to Concord Road (18.53) – (mm 15.93 – 18.53)
- Daily 9 a.m. – 3 p.m., We anticipate needing intermittent stoppages of traffic, and/or temporary lane closures (one direction at a time) between the hours of 9AM and 3PM Monday thru Friday, and possibly on Saturday (although not currently scheduled) for various construction activity including paving and utility work throughout the project.
We are planning on having extended delays and possible lane closures for construction activities for the following side roads: Ashby Dr. Holly Tree Gap Rd, Long St., West Concord, Wikle Rd. and Mt. View Rd.
WILLIAMSON COUNTY SR 96
Local Programs: Sr-96 West Multi-Use Trail
- 2/10 – 2/11, 8 p.m. – 5 a.m., There will be a lane closure on SR-106 for water line relocation
Grading, drainage, construction of bridges and signals on SR 96 from east of Arno Rd (LM 14.72) to SR 252 (Wilson Pk) (LM 20.62).
- Daily, 9 a.m. – 3 p.m., There will be lane closures and brief stoppages of traffic for utility relocations and grading work.
WILLIAMSON SR 106
The replacement of a 60″ corrugated metal pipe on US 431 (SR 106) at MM 13.65
- Continuous, Continuous Full Road closure on SR 106 (Lewisburg Pk) between Carnton Ln and Eastern Flank Cir until June 30th for culvert replacement. Traffic will be detoured via SR 6 (Columbia Ave) and SR 397 (Mack Hatcher Pkwy). Detour signs will be in place.
WILLIAMSON COUNTY SR 397
The grading, drainage, construction of bridges, retaining walls, and paving on SR 397 (Mack Hatcher Pkwy) from south of SR 96 to east of US 431 (SR 106)
- Daily, 9 a.m. – 3 p.m., There will be temporary lane closures in both directions on Mack Hatcher at Hillsboro Road for punchlist items and also on Hillsboro Road northbound to perform punchlist items.
- Daily, 9 a.m. – 3 p.m., There will be lane closures in both directions on Highway 96W between Front Street and Boyd Mill Avenue for punchlist items. Flaggers will be utilized.
WILSON COUNTY SR 171
Bridge widening on SR 171 over I-40, mm 4.57 – 5.29
- Nightly, 8 p.m. – 5 a.m., SR 171 will have intermittent lane closures for bridge widening activities.
>>MAINTENANCE & UTILITIES
*NOTE: All pothole repairs are weather contingent
DAVIDSON COUNTY I-24
Emergency pothole repairs
- Daily, 9 a.m. – 3 p.m, Single, alternating lane and shoulder closures in both directions of I-24 from MM 32 to MM 36 for emergency pothole repairs.
- Daily, 9a.m. – 3 p.m., Single, alternating lane and shoulder closures in both directions of I-24 between SR 171 OHB exit and Haywood Lane exit 57 for emergency pothole repairs mm 56 – 63.22
DAVIDSON COUNTY I-40
Emergency Pothole Repair
- Daily, 9 a.m. – 3 p.m., Single, alternating lane and shoulder closures in both directions of I-40 from McCrory Lane exit 192 to SR 251 OHB exit 199 for emergency pothole repairs. (mm 191.80 – 201)
DAVIDSON COUNTY I-440
Emergency Pothole Repair
- Daily, 9 a.m. – 3 p.m., Ramp, lanes and shoulder closure of I-440E at I-65 S for emergency pothole repairs. MM 5
SMITH COUNTY I-40
Emergency In-place paving on I-40 in Smith County
- Daily, 8 a.m. – 10 p.m., I-40 EB and WB will have intermittent lane closures for emergency paving activities. Mm 250 – 258
DAVIDSON COUNTY SR 155
Milling and Paving
- Daily, 9 a.m. – 3 p.m., Various lane and shoulder closures for milling and paving on SR 155 westbound. (mm 18 – 19)
DAVIDSON COUNTY SR 1
Roadway repair/patching
- Daily, 9 a.m. – 3 p.m., Alternating lane and shoulder closures in both directions of Harding Pike from Vine Ct. to Woodlawn Dr. for roadway repair and patching.
DAVIDSON COUNTY SR 24
Roadway patching
- Daily, 9 a.m – 3 p.m. Alternating lane closures in both directions of Charlotte Pike from 51st Ave. to 28th Ave. for roadway patching.
Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity. Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather.
From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel.
As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text or talk on a cell phone while behind the wheel.
Subscribe to our FREE Newsletter!